Weekly Update 7/23/26

Ice and water shield going in and light poles/baptismal have been delivered!
Photos, left to right: Getting all the islands filled around the parking lot with topsoil; Ice and water shield going on the roof before we do the standing seam to help keep the building protected; Got the light poles delivered today; Standing seam, metal roof being bent on site; Ice and water shield almost complete on Southside of church; View of front of church; Got our baptismal tub in; Tyvek complete.