New Church Building
In 2019, the Lord graciously provided Northlake Bible Church with 11.5 acres of land located on Highway 407 across from Faught Road. This property was generously purchased by our sending church, Countryside Bible Church. Since then, God has faithfully continued to provide the financial resources necessary to move forward with developing the site for future ministry.
While Lance Thompson Elementary School has been a wonderful place for our church to gather, we are very excited for the possibility of having our own permanent place to worship very soon. It has always been our desire to root ourselves in this community as a beacon for the gospel not only for the immediate future but until our Lord returns! A physical building will be an important part of making that desire a reality.
The building we are designing will allow us to not only gather for worship each Sunday, but will also include spaces designed for children’s ministry, youth ministry, adult discipleship and fellowship.
While Lance Thompson Elementary School has been a wonderful place for our church to gather, we are very excited for the possibility of having our own permanent place to worship very soon. It has always been our desire to root ourselves in this community as a beacon for the gospel not only for the immediate future but until our Lord returns! A physical building will be an important part of making that desire a reality.
The building we are designing will allow us to not only gather for worship each Sunday, but will also include spaces designed for children’s ministry, youth ministry, adult discipleship and fellowship.
New Building Updates
Weekly Update 8/20/26
August 20th, 2026
Exterior hardy siding has begun! Photos, left to right: Hardy siding has started on the south side of the church; Dumpster pad poured; Hardy siding progress; Drywall grid being installed in 1st floor restrooms.......
Weekly Update 8/13/26
August 13th, 2026
Sanctuary framing complete and electrical coming along! Photos, left to right: Rear sanctuary wall is finally framed; Electrical Box; Closing walls and getting ready for taping; First floor lobby; Getting power from electrical room to front of building; Starting to put on standing seam roof; Coserv is back on site setting last power pole for permanent power; Standing seam roof progress on north si...
Weekly Update 8/6/26
August 6th, 2026
Drywall installation has begun, and poles for permanent power being installed! Photos, left to right: Drywall and insulation being put in; Welders welding I-beam for speakers and stage lighting; Pouring light pole bases; One of the back sidewalks was poured to have a place for AC units; Back sidewalk poured; Getting standing seam sheets ready to go on roof; Extra storage area; View of street side ...
Weekly Update 7/30/26
July 30th, 2026
Building now ready for any rain, and light poles being installed! Photos, left to right: ......
Weekly Update 7/23/26
July 23rd, 2026
Ice and water shield going in and light poles/baptismal have been delivered! Photos, left to right: Getting all the islands filled around the parking lot with topsoil; Ice and water shield going on the roof before we do the standing seam to help keep the building protected; Got the light poles delivered today; Standing seam, metal roof being bent on site; Ice and water shield almost complete on S...
Weekly Update 7/17/26
July 17th, 2026
Starting to look more like a church! Photos, left to right: Stone delivered; Getting the front entry soffit in; Hanging the FPBs; Duct going up on second floor; More final grading of lot around building; More sheathing going up on north side of building; Getting all the exterior sheeting put up/starting to look more like a church.......
Weekly Update 7/9/26
July 9th, 2026
Parking lot ready for vehicles; and more sheathing! Photos, left to right: Parking lot is cured and ready for vehicles; Roof sheathing starting; Sheathing.......
Weekly Update 7/3/26
July 3rd, 2026
Lots of framing this week! Photos, left to right: Side view; Another view; Front of the church from the inside second floor; Sanctuary from inside; Interior door frames being set; Northside church entry being framed; Getting sheathing on front of church; Front entry all framed.......
Weekly Update 6/25/26
June 25th, 2026
Finishing parking lot and starting electrical. Photos, left to right: Starting metal decking on light gauge trusses; Approach from 407 all formed; Safety truck with flashing warning lights to block shoulder for workers to tie in approach from 407; New approach coming in off Hwy 407; Gas test station relocated outside concrete approach; Electrical wall rough started/all boxes going in on first floo...
Weekly Update 6/19/26
June 19th, 2026
Safety signage on 407, new temporary road, and trusses. Photos, left to right: Cutting the lines in the parking lot; Sheeting going up; Setting the last trusses; Compacting new temp road into site; New rock for temp road going in; Rock for temp road; First floor interior framing; First floor restrooms framed and plumbing rough in; Approach to 407 getting cut in; Safety signage and shoulder closed ...
Our Goal
By the Lord’s gracious provision through the means of your faithful and sacrificial giving we have met and exceeded our goal of four million dollars!
We are now finalizing plans with our builder and the Town of Northlake in order to move forward towards breaking ground on our new building as quickly as possible.
It is truly remarkable to see how God has brought us to this point, and we are filled with gratitude and anticipation for what He will continue to do through Northlake Bible Church for His glory.
Thank you for your generosity, your prayers, and your partnership in this building project. Further updates will be posted as we have more information.
Psalm 115:1
Not to us, O Lord, not to us, but to Your name give glory because of Your lovingkindness, because of Your truth.
We are now finalizing plans with our builder and the Town of Northlake in order to move forward towards breaking ground on our new building as quickly as possible.
It is truly remarkable to see how God has brought us to this point, and we are filled with gratitude and anticipation for what He will continue to do through Northlake Bible Church for His glory.
Thank you for your generosity, your prayers, and your partnership in this building project. Further updates will be posted as we have more information.
Psalm 115:1
Not to us, O Lord, not to us, but to Your name give glory because of Your lovingkindness, because of Your truth.